SADOVAYA (SGR): MAY 2012 PRODUCTION UPDATE - raport 16
Raport bieżący nr 16/2012
Podstawa prawna:
Inne uregulowania
Sadovaya Group S.A., a joint stock company under Luxembourg law, with registered office at 412F, route d’Esch, L-2086 Luxembourg, registered in the Luxembourg Register of Companies under No. B 153.489, (the "Company"), hereby provides update on coal production in May 2012:
� Coal sales decreased by 13.1% month-on-month on slowdown of electricity consumption from industry and households
� Coal mining increased by 3.4% month-on-month and 41.1% year-on-year
Development of module enrichment complex (MEC) construction (please find photos of construction progress on the next page):
� We started to assemble steelworks of the main building and continued to assemble steelworks for other MEC buildings
� Supply of technological equipment is ongoing (conveyors, separators)
� We plan to start testing works of MEC with first coal output in July, 2012
For detailed information of coal production and MEC photos please refer to attached file.
Legal grounds: article 56.1 in connection with article 56.6 of the Act of 29 July 2005 on the public offering, conditions governing the introduction of financial instruments to organised trading system and on public companies.
Załączniki:
Plik;Opis
Viktor Chornogor - Internal auditor